Re: Update on the SJP works
Plan A was still within the constraints of our own land. Plan A also planned for the stand to be moved forward. The current plans are a cheap option which avoided the costs in excavating a greater volume of soil and to a lower level. Retaining walls would have been built with Plan A - obviously avoided with the current plans.Can I ask when plan a was unveiled had network rail been approached? Those plans were for a stand which extended a lot further down the touchline.